Project Name | New O2 GAN Compressor Electrical & Instrumentation Works |
---|---|
Project Duration | Ongoing |
Project Value | S$ 200,000.00 |
Project Type | Engineering, Procurement & Construction |
Scope of Work | MV Cable Laying & Termination, Cable tray and ladder installation, Ventilation Fan duct fabrication and installation, instrument installation, testing & commission. |
Client | Air Liquide Singapore Pte Ltd |
Main Contractor | Yeohong Construction & Engineering Pte Ltd |
#1: | ||
---|---|---|
Project Name | Replace Existing Control Valves, New Differential Pressure transmitter, TemperatureSensor in 02 Compressor C40 & C41 Shutdown Job | |
Project Duration | October 2019- November 2019 | |
Scope of Work | Replace with new control valve, airline tubing modification, control valve testing and commissioning, Temperature RTD sensor installs, loop test& testing, Differential transmitter installation, loop test, new sample line laying & testing, Cable laying, loop test, cable glanding & Cable termination | |
Client | Air Liquide Singapore Pte Ltd | |
Main Contractor | Yeohong Construction & Engineering Pte Ltd |
#2: | ||
---|---|---|
Project Name | Replace Existing Control Valves, New Differential Pressure transmitter, Temperature Sensor in 02 Compressor C40 & C41 Shutdown Job | |
Project Duration | October 2019- November 2019 | |
Scope of Work | Replace with new control valve, airline tubing modification, control valve testing and commissioning, Temperature RTD sensor installs, loop test& testing, Differential transmitter installation, loop test, new sample line laying & testing, Cable laying,loop test, cable glanding & Cable termination | |
Client | Air Liquide Singapore Pte Ltd | |
Main Contractor | Yeohong Construction & Engineering Pte Ltd |
#3: | ||
---|---|---|
Project Name | Removal of 400V LV Motors from foundation and after servicing install back during Tuaspring Shutdown 2020. | |
Project Duration | February 2020- March 2020 | |
Scope of Work | Removal and Installation of Low voltage Motors from foundation. Power cable Disconnection.400V low voltage motors disconnect from the foundation and transfer to Unloading area. Power cables to be secure properly with insulated bags and avoid water ingress. | |
Client | Tuaspring Pte Ltd |
#4: | ||
---|---|---|
Project Name | Structural Earthing & BCA Submission | |
Project Duration | October 2019 n | |
Scope of Work | Providing Piping Structure Lightning Protection earthing, BCA Submission | |
Client | Air Liquide Singapore Pte Ltd | |
Main Contractor | Yeohong Construction & Engineering Pte Ltd |